Qualifications:

Under contract and completed Projects by

Wells & Water Systems, Inc.

Robert J. Kohlmeier and/or Employees

 

Work completed for various Towns, Villages, Counties, Agricultures, Municipalities, State and Federal Agencies. List of Engineers, phone numbers and contacts

 

Description of Work:

Collier County                                                                       In progress                2018

Golden Gate Wellfield         

Collier County

  • Acidizing  2 Production Wells
  • Well Rehabilitation
  • Pump Removal and Reinstalling Well Heads
  • Restore - New Piping
  • Pump Testing

 

Sanibel Inland Well –IWA H-14                                         Completed     June    2018

  • Well Rehabilitation
  • Pump Removal  Well Heads Reinstallation
  • Well acidizing
  • Restore  New Piping and Site Cleaning
  • Conduct Specific Capacity
  • Drawdown Test Pump Development

 

Old Collier County                                                               In Progress                 2018

Old Collier Golf Club Well LH-1 Ac Rehab

  • Well Rehabilitation
  • Pump Removal and
  • Reinstalling Well Heads
  • Well Acidizing
  • Restore Site  
  • Conduct Specific Capacity
  • Drawdown Test Pump Development

 

Collier County- Well Rehabilitation Project          Completed    April                2018   

NESA Orange Tree

  • Well Rehabilitation Develop Open Hole
  • Conduct Specific Capacity and Steps Drawdown Test
  • Pump Development and Reinstallation  
  • Disconnection and Assist in Bacteriological Clearance

 

Colony Country Club                                                           Completed June        2018   

Well Rehabilitation Project

  • Drill Pilot Hole
  • Well Development
  • Drill and Install 16 inch Casing
  • Air Develop
  • Conduct Specific Capacity and Steps Drawdown Test
  • Piping
  • Installation of New Electric Boxes

 

Bonita Springs Utilities                                                                                                2018

Well Rehabilitation Project                                               

  • Salt Down Well
  • Installation of New Pump
  • Well Development

 

Raptor Bay Pump Development and Reinstall Completed                       May       2017

  • Pre/Post Video Logs
  • Four Shallow Wells to 40-feet
  • Pull Pump
  • Brushed/Cleaned Well Casings
  • Air Develop
  • Acidize with 5,000 Gallons Hydrochloric Acid
  • Remove Spent Acid
  • Pre/Post Pump Test Reinstall pump
  • All Wells Volumes Increased 90%

 

Deep Well - One Well to Lower Hawthorne Completed                           Jun 11, 2017

  • Pre-test Flow was 1.3 GPM
  • Post Test Flow 98 GPM
  • Video Log
  • Acidize with Over 10,000 Gallons of Hydrochloric Acid
  • Installed new Well Head and Valves
  • Entire Project Finished Ahead of Schedule and at Budget

 

Old Collier Golf Course

Immokalee Road, Naples, Florida                                                               July, 2017

  • Lower Hawthorne Well
  • Pre Test
  • Pull Pump
  • Acidize with 8,000 gallons of hydrochloric acid
  • Post Flow Test
  • Reinstall Pump -Video logs  -Flow increased more than 80%

Collier County / Quality Enterprises                           Completed                          2016

  • Salt Down Wells (New Valves, Backflow, Gaskets)
  • Bolts (spacers, spool pieces)
  • Remove salt & Bacterial Clearances

 

Marco Island Marriott Injection                                                                             2016

Well & Supply Rehabilitation   

  • Acidize the Injection and Supply Wells
  • Replace Supply Pump
  • Add Meters & Piping
  • New Electrical Panel & Controls

 

Collier County Quality Enterprises                                                                        2016

  • Install New Pump and Piping
  • Valves, Backflow Primary/Secondary

 

Naples, Florida - Pulte Construction                                                   

Winding Cypress

  • Video Log Two Wells
  • Investigate Flowing Well
  • Install Inflatable Packer to Stop Flow
  • Abandon both Wells

 

North RO Aquifer Improvements Well Rehabilitation

Acidize and Pumps

  • Acidize Two Wells, Five Well Disinfections
  • Bacteriological Clearance Pull & Reinstall Pumps

 

Wells 16 & 17 Collier County                                                                                  2016

  • Salt Down Wells
  • Install Valves/Backflows
  • Weld and Replace Piping     
  •  Pump off Salt Solution
  • Well Clearance (Bacteriological)

 

City Of Fort Myers –Wellfield Development                                                            2015

Phase 2

  • Public Water Supply Wells Rehabilitation
  • Improvement of PWS Wells
  • Acidizing  for PWS
  • Pump Development Wells
  • Pump Testing
  • Geophysical Logging
  • Installing new Piping System and Valves - Wellheads and Controls - Reinstalled

 

Seacoast Utility Authority     FL                              Completed                      2014 - 2015

Replacement of Well N. 9

Surficial Aquifer Wells Hood Rd

  • Public Water Supply Wells ( 24 inc wells)
  • Pump Development wells
  • Air development
  • Pump Testing
  • Depth to  200
  • Wellhead and Flanges

 

USACE Picayune Strand Restoration Project      Completed                                  2014

Miller Pump Station, Collier County                                                        

  • New Public Water Supply Well
  • Pump Development
  • Pump Test and Water Quality Testing
  • Filter and Equipment
  • Pumps (Piping, Controls, Electrical) Underground Utilities

 

City Of Fort Myers –Wellfield Development            100% completed           2014-2015

Phase 1

  • Public Water Supply Wells Rehabilitation
  • Improvement of PWS Wells
  • Acidizing  for PWS
  • Pump Development Wells
  • Air development
  • Pump Testing
  • Geophysical Logging
  • Piping (valves-wellheads and controls)

 

City of LaBelle, FL                                                               Bonded                           2013

Water Treatment Facilities (PWS)

Well #2 and #3 Raw Water

  • Two Public Water Supply
  • Casing 16” 
  • 800 ft Wells
  • Well Logging
  • Cementing
  • Pump Test and Water Quality Testing
  • Controlled Air Development for 2 Production Wells

 

City of Coral Springs, FL                  Completed    Bonded                            2012-2013

Forest Hills Wellfield Rehabilitation

  • Public Water Supply Well
  • 30 Inches Surface -24 Intermediate 
  • 16” casing 16”  125 Depth
  • Well Logging
  • Cementing
  • Acidize  up to 9 Wells
  • Pump Test and Water Quality Testing
  • Well Abandonment 
  • Controlled Air Development for 2 Production Wells

 

Palm Beach County, FL                   Completed    Bonded                             2012-2013

  • Public Water Supply Well
  • 30 Inches Surface -24 Intermediate 
  • 16” casing 16”  125 Depth
  • Cementing
  • Conduct Video Logging
  • Well Abandonment - Well Development
  • Pump Test - Water Quality Testing

 

Well Abandonment and Well Rehabilitation Projects Competed by

Wells &Water Systems, Inc.

Robert J. Kohlmeier and/or Employees

 

Bonded Job as a Prime Contractor:

  South Florida Water Management District 

  City of Cape Coral - City of Fort Myers

  Lee County (cleaning and abandonment of an old Oil well approximately 2500 feet deep)

  City of Ormond Beach

  Verna Well Field , Sarasota (1,000 feet deep)

  Sanibel Inland

 

Contractors:  

  City of Cape Coral

  City of Naples

  Harbor Heights Water Associates

  Indian Reservation

  Ocean reef Club

  Sanibel Island

Agriculture Work throughout Florida:  

  Alico Inc.

  Baron Collier - Collier County

  Dole Pinnacle

  USDA

  US Sugar

 

Additional information on others wells completed in the last five years throughout the state of Florida. Details are available upon request.